The industrial complex ALFA
The industrial construction in order to rise an automatic mechanisation
The industrial construction in order to rise an automatic mechanisation
Investor:
ALFA výroba jednoúčelových strojů s.r.o.
Location:
Písek (The Czech Republic)
Project duration:
04/2018 – 05/2018
Project in numbers:
59 pcs (total amount of precast structures)
10,5 tons (the biggest weight of precast beam)
The client asked for a solution to accelerate the process of construction. Two of our division was included into that task – RC concrete and PRECAST str. Over just 1 month we accomplished the construction and handed over to the client.
All precast structures for multi span industrial building were executed and delivered from our facility in the Czech Rep. – Kolín, where we specialises in bespoke industrial production of precast structure with utilisation in many areas. There were built in 18pcs of columns and more than 30pcs of beams in the double-navy hall.